2021 Commercial Tenant Improvement Permit Times

We’ve contacted each municipal licensing department to understand current estimates on how long permits applications are taking. This provides some insight on the current demand and wait times.

Tenant Improvement permits are required for any new construction, interior and exterior alteration, addition to a structure, temporary building/structures, accessory buildings and change of use to an existing building.

  • Vancouver – 10-12 Weeks
  • North Vancouver – 10+ Weeks
  • Richmond – 8+ Weeks
  • Burnaby – 12+ weeks
  • Surrey - 10+ Weeks
  • Delta – Pre Covid 1 Month (Now 10+ weeks)
  • Coquitlam – 3 weeks
  • Langley – 6 Weeks

This is just a reference, but before making key decisions on your next project.